Plant Pipeline Retrofit

Home  /  Projects  /  Pipeline Retrofit

Pipe Welding

120 Joints,
One Weekend

Welder joining process pipe in the plant

The Challenge

A food processing plant in Queens had a 54-hour shutdown window to replace corroded carbon lines with 304 stainless — overhead runs, washdown zones and a hard Monday 5am restart. Any missed joint meant lost production.

Our Approach

Two crews leapfrogged the line: one cutting and fitting ahead, one welding behind with purged TIG roots. Every joint was numbered on an isometric map, hydro-tested in sections and signed off with the plant engineer before handover — 42 hours in, 12 hours ahead of schedule.

  • 120 purged TIG joints, 2 to 6 inch
  • Two-crew leapfrog sequence
  • Sectional hydro-tests, witnessed
  • Full isometric weld-map turnover